Modification Of Idu, Oshie and Ebocha Slug Catchers at OB/OB Gas Plant, Nigeria
This project entails in-plant modification of pipelines to commingle other pipelines. There is a need to create a bypass line of 10’’ pipe linking Idu, Oshie and Ebocha pipelines to enable the 3 pipelines to use the slug catcher of Idu at OBOB gas plant. This was done because the slug catchers of Oshie and Ebocha was bad. The project was done in 2023 for NAOC at OBOB gas plant in Omoku, Port Harcourt, Rivers State.
In the course of the project, there is need to perform Hot Tap operation on the Idu line because it was live and shut down was not feasible.